Introduction:  
Smart Grid project  
Aug, 2010  
Tokyo Electric Power Services Co., LTD  
(TEPSCO)  
Copyright © Tokyo Electric Power Services Co., LTD  
2
Contents  
1. Overview of Smart Grid  
1.1 Overview  
1.2 Current activity of oversea countries  
2. Introduction of Smart Grid Components  
2.1 Distribution Automation system (DAS)  
including Auto Meter Reading (AMR)  
2.2 Distribution loss reduction by DAS and AMR  
2.3 Peak Cut by Demand Response (DR)  
2.4 Solar Power as renewable energy  
3. Proposal for next step  
Copyright © Tokyo Electric Power Services Co., LTD  
3
1. Overview of Smart Grid  
Copyright © Tokyo Electric Power Services Co., LTD  
4
Overview of Smart Grid  
Explanatory notes:  
SCADA  
Pumped-storage  
Wind Power (large scale)  
Nuclear Power  
Thermal Power  
Transmission network  
Solar Power (large scale)  
Hydro Power  
Network Connection of Renewable Energy  
Substation  
Battery  
Wind Power (small scale)  
Solar  
Distribution office  
Distribution Automatic System (DAS)  
Automatic  
LBS  
Distribution Network  
Solar  
Power Conditioner  
Battery  
AMR for  
Apartment building  
Monitoring of  
Voltage  
Smart Meter  
Battery by EV  
Auto Meter Reading  
(AMR)  
AMR for house  
Copyright © Tokyo Electric Power Services Co., LTD  
5
1.1 Overview  
Definition of Smart Grid  
<IEC (TC8) 60050-617>  
Electric Power network that utilizes two-way communication and control  
technologies, distributed computing and associated sensors, including  
equipment installed on the premises of network users*.  
* including power generation companies and consumers  
Note: Smart grid are intended to increase the quality of the electricity supply by  
providing functions such as:  
-Network automation  
-Power quality management  
-Distributed generation management  
-Demand response  
-Smart metering  
-Preventive maintenance  
-Outage Management  
-Energy storage management  
Copyright © Tokyo Electric Power Services Co., LTD  
6
1.1 Overview  
Effects and advantages by smart grid projects  
• Effective Power supply → Reduce construction of Power Generators  
- improvement of distribution losses by DAS and AMR  
- peak-cut by DR  
- Application of renewable energy (Solar, Wind, Fuel cell etc)  
• Improvement of reliability for Distribution network  
- reduction of outage duration by DAS  
• Up-grading of ICT technology for Local engineers  
Problem by connecting renewable power to Distribution network:  
-Balance between supply and demand under weather condition  
-Rising voltage on end of Distribution network  
-Dangerous maintenance works by connection renewable power  
Energy management by using communication network of DAS and AMR  
In future, this communication network can be useful for HA (Home Automation and  
Electric Vehicle (EV) as battery.  
Copyright © Tokyo Electric Power Services Co., LTD  
7
1.1 Overview  
Project components for Smart Grid  
Smart Grid consists of the following Technologies / Components .  
Experience  
High technology of Development  
Projects  
Japan  
(Completion)  
DAS  
◎
◎
◎
AMR (Auto Meter Reading)  
DR (Demand Response)  
◎
○
○
○
○
○
Renewable energy(Solar、  
Wind、Fuel Cell etc)  
○
○
○
Battery(Lithium-ion、 )  
△
◎
△
HA  
△
△
○
○
△
△
EV (as battery)  
Communication network of DAS can be used for backbone network of smart grid.  
Communication network of AMR can be used for last one-mile network of smart grid.  
Copyright © Tokyo Electric Power Services Co., LTD  
8
1.1 Overview  
Concept of DAS  
< Concept of DAS >  
DAS Control Centre  
OH  
equipment  
Fiber Optic  
RTU  
Fiber Optic  
Substation  
UG equipment  
(Kiosk/Distributor)  
Copyright © Tokyo Electric Power Services Co., LTD  
9
1.1 Overview  
Concept of AMR  
< Concept of AMR >  
2nd side of DT  
Smart Meter  
Customer  
Back bone network  
Control center for  
AMR (DAS)  
Communication  
network of DAS  
(Fiber Optic)  
ZigBee for last  
one mile  
communication  
Copyright © Tokyo Electric Power Services Co., LTD  
10  
1.1 Overview  
System Configuration of Smart Grid projects  
SCADA  
Energy management  
Data link  
Energy  
management  
Wind Power  
Mega Solar  
DAS  
DSM  
AMR  
FEP  
Backbone network  
Battery  
SVR  
(Fiber optic)  
Solar  
RTU  
Last one-mile  
(radio:ZigBee)  
Smart Meter  
Smart Meter(AMR/DSM)  
EV Solar Cell  
HA  
Battery  
Copyright © Tokyo Electric Power Services Co., LTD  
11  
1.2 Current Activities of oversea countries  
Country  
Power company  
Target by Smart Grid for  
Power company  
Reliability of network is not so good  
due to separation of Generation /  
transmission / Distribution and many  
Distribution Company (more than  
3000).  
-High reliability by using Information  
Communication Technology (ICT)  
USA  
DAS  
-Improve non-technical loss  
-New business by using interactive  
communication  
-International connection based on  
every country’s network  
-Acceleration of renewable energy  
-Improve non-technical loss  
EU  
-Fluctuation of Power (Frequency)  
due to Wind power of large capacitor  
in Denmark/Netherlands  
-Construction of Infrastructure for  
Electric Vehicle  
High reliability of Power network due -Countermeasure when a lot of  
to SCADA, DAS and redundant  
network  
renewable energy will connect to  
Distribution network  
-Energy management for consumer  
side  
Japan  
Copyright © Tokyo Electric Power Services Co., LTD  
12  
1.2 Current Activities of oversea countries  
Country  
Power company  
Plan for smart grid  
-DAS has been operated in 6 areas in PEA  
since 2004.  
-DAS will be expanded to whole areas in  
PEA by 2012. (In addition 7 areas)  
-AMR has been operated in 30,000  
customers in PEA.  
-AMR will be expanded to 50,000  
customers by 2012.  
Thailand  
-200MW of renewable energy has been  
operated in PEA. (Biofuels: 60-70%, Solar:  
5-10%, Wind power etc)  
-DAS is under trial stage.  
-AMR is also under trial stage.  
-DAS will be applied to Ho Chi Minh city  
by using Fiber Optic.  
-Smart Grid including AMR / DR / Solar  
will be applied to large city.  
-Renewable energy will be increased up  
to 5% by 2020.  
-Solar power is installed in Quang Binh  
province from 2010.  
-Renewable energy (Wind /Solar /Biofuels  
etc) is 3% of commercial electricity capacity.  
Vietnam  
India  
-Indian government started to improve  
Distribution loss and the reliability by  
APDRP (10,000MUS$).  
-DAS / AMR / GIS will be expanded to  
large cities by using APDRP.  
-Smart community city plan will be started  
-DAS is under construction in Bangalore city. to apply for 4 cities as model projects.  
This plan will be promoted by the support  
of Japanese finance under construction of  
high speed railway project.  
-AMR and Pre-paid system have been  
applied as model project.  
Copyright © Tokyo Electric Power Services Co., LTD  
13  
2.1 Distribution Automation system  
(DAS)  
including Auto Meter Reading  
(AMR)  
Copyright © Tokyo Electric Power Services Co., LTD  
14  
Contents  
1. Introduction of DAS  
2. Advantages of DAS / DSM  
3. Network System of DAS  
• Overhead Network System  
• Underground Network System  
• Communication System  
4. Distribution Automation SCADA System  
Copyright © Tokyo Electric Power Services Co., LTD  
15  
1. Introduction of DAS / DSM /  
AMR  
Copyright © Tokyo Electric Power Services Co., LTD  
16  
What is DAS ?  
• DAS improve reliability of Distribution power  
utilities by reduction of outage duration.  
- Automatic isolation of faulty section  
- Quick Recovery for healthy sections  
- Monitoring for distribution network in  
real time  
• DAS contribute to improve technical / non-  
technical losses.  
• DAS can connect to GIS (Giographic  
Information System), AMR (Auto Meter  
Reading) and DSM (Demand Side  
Management).  
Copyright © Tokyo Electric Power Services Co., LTD  
17  
Contribution to Society  
Reduction of outage by DAS will…  
• Attract Manufacturing Companies by improving and  
ensuring the quality and their productivity  
• Avoid Social Panic, such as hospital outage and  
traffic stoppage  
• Decrease of CO2 by diesel  
engine which is used during  
outage  
Copyright © Tokyo Electric Power Services Co., LTD  
18  
Outage Time Around the World  
(minute/year)  
Figure. Average Outage Time per Customer  
500  
450  
400  
350  
300  
250  
200  
150  
100  
50  
462  
Key Point  
- Japanese DAS provides the shortest  
outage time in the world  
- Japan has over 35 years experience on  
Distribution Automation  
90  
77  
58  
4
0
Example (without  
DAS)  
USA  
UK  
FRANCE  
JAPAN  
(TEPCO)  
India: 5,000 minutes in Bangalore (2005), Indonesia: 1,055 minutes in 2009  
Reference: USA - IEEE Transactions on Power Delivery Jan.1999, UK - Ofgerm report 1999/2000 Jan. 2000  
FRANCE - EDF Annual Report 2000, JAPAN - the Federation of Electric Power Companies (FEPC) report 2001  
Copyright © Tokyo Electric Power Services Co., LTD  
19  
Japan’s Experience on DAS  
Present Condition  
1970  
1980  
1990  
2000  
Recloser System  
Manual Switch  
1972  
O
V
E
R
H
E
A
D
Aim of Project  
Oil Switch Vacuum Switch(VS) / Air Switch(AS)  
⇒
Simplify DAS  
Automatic Switch (VS/AS/GS)  
VS/AS  
⇒
DAS  
SCADA System using Communication line  
U
N
D
E
R
G
R
O
U
N
D
Manual Underground Switch (5ways)  
Oil switch VS / AS  
⇒
Automatic Underground Switch based on DAS  
Copyright © Tokyo Electric Power Services Co., LTD  
20  
Tải về để xem bản đầy đủ
pdf 152 trang myanh 27440 Free
Bạn đang xem 20 trang mẫu của tài liệu "Bài giảng Green energy course syllabus - Chapter 7: Smart grid project - Nguyễn Hữu Phúc", để tải tài liệu gốc về máy hãy click vào nút Download ở trên

File đính kèm:

  • pdfbai_giang_green_energy_course_syllabus_chapter_7_smart_grid.pdf