Bài giảng Green energy course syllabus - Chapter 7: Smart grid project - Nguyễn Hữu Phúc
Green Energy Course-
Renewable Energy Systems
Biên sọan: Nguyễn Hữu Phúc
Khoa Điện- Điện Tử- Đại Học Bách Khoa TPHCM
Introduction:
Smart Grid project
Aug, 2010
Tokyo Electric Power Services Co., LTD
(TEPSCO)
Copyright © Tokyo Electric Power Services Co., LTD
2
Contents
1. Overview of Smart Grid
1.1 Overview
1.2 Current activity of oversea countries
2. Introduction of Smart Grid Components
2.1 Distribution Automation system (DAS)
including Auto Meter Reading (AMR)
2.2 Distribution loss reduction by DAS and AMR
2.3 Peak Cut by Demand Response (DR)
2.4 Solar Power as renewable energy
3. Proposal for next step
Copyright © Tokyo Electric Power Services Co., LTD
3
1. Overview of Smart Grid
Copyright © Tokyo Electric Power Services Co., LTD
4
Overview of Smart Grid
Explanatory notes:
SCADA
Pumped-storage
Wind Power (large scale)
Nuclear Power
Thermal Power
Transmission network
Solar Power (large scale)
Hydro Power
Network Connection of Renewable Energy
Substation
Battery
Wind Power (small scale)
Solar
Distribution office
Distribution Automatic System (DAS)
Automatic
LBS
Distribution Network
Solar
Power Conditioner
Battery
AMR for
Apartment building
Monitoring of
Voltage
Smart Meter
Battery by EV
Auto Meter Reading
(AMR)
AMR for house
Copyright © Tokyo Electric Power Services Co., LTD
5
1.1 Overview
Definition of Smart Grid
<IEC (TC8) 60050-617>
Electric Power network that utilizes two-way communication and control
technologies, distributed computing and associated sensors, including
equipment installed on the premises of network users*.
* including power generation companies and consumers
Note: Smart grid are intended to increase the quality of the electricity supply by
providing functions such as:
-Network automation
-Power quality management
-Distributed generation management
-Demand response
-Smart metering
-Preventive maintenance
-Outage Management
-Energy storage management
Copyright © Tokyo Electric Power Services Co., LTD
6
1.1 Overview
Effects and advantages by smart grid projects
• Effective Power supply → Reduce construction of Power Generators
- improvement of distribution losses by DAS and AMR
- peak-cut by DR
- Application of renewable energy (Solar, Wind, Fuel cell etc)
• Improvement of reliability for Distribution network
- reduction of outage duration by DAS
• Up-grading of ICT technology for Local engineers
Problem by connecting renewable power to Distribution network:
-Balance between supply and demand under weather condition
-Rising voltage on end of Distribution network
-Dangerous maintenance works by connection renewable power
Energy management by using communication network of DAS and AMR
In future, this communication network can be useful for HA (Home Automation and
Electric Vehicle (EV) as battery.
Copyright © Tokyo Electric Power Services Co., LTD
7
1.1 Overview
Project components for Smart Grid
Smart Grid consists of the following Technologies / Components .
Experience
High technology of Development
Projects
Japan
(Completion)
DAS
◎
◎
◎
AMR (Auto Meter Reading)
DR (Demand Response)
◎
○
○
○
○
○
Renewable energy(Solar、
Wind、Fuel Cell etc)
○
○
○
Battery(Lithium-ion、 )
△
◎
△
HA
△
△
○
○
△
△
EV (as battery)
Communication network of DAS can be used for backbone network of smart grid.
Communication network of AMR can be used for last one-mile network of smart grid.
Copyright © Tokyo Electric Power Services Co., LTD
8
1.1 Overview
Concept of DAS
< Concept of DAS >
DAS Control Centre
OH
equipment
Fiber Optic
RTU
Fiber Optic
Substation
UG equipment
(Kiosk/Distributor)
Copyright © Tokyo Electric Power Services Co., LTD
9
1.1 Overview
Concept of AMR
< Concept of AMR >
2nd side of DT
Smart Meter
Customer
Back bone network
Control center for
AMR (DAS)
Communication
network of DAS
(Fiber Optic)
ZigBee for last
one mile
communication
Copyright © Tokyo Electric Power Services Co., LTD
10
1.1 Overview
System Configuration of Smart Grid projects
SCADA
Energy management
Data link
Energy
management
Wind Power
Mega Solar
DAS
DSM
AMR
FEP
Backbone network
Battery
SVR
(Fiber optic)
Solar
RTU
Last one-mile
(radio:ZigBee)
Smart Meter
Smart Meter(AMR/DSM)
EV Solar Cell
HA
Battery
Copyright © Tokyo Electric Power Services Co., LTD
11
1.2 Current Activities of oversea countries
Country
Power company
Target by Smart Grid for
Power company
Reliability of network is not so good
due to separation of Generation /
transmission / Distribution and many
Distribution Company (more than
3000).
-High reliability by using Information
Communication Technology (ICT)
USA
DAS
-Improve non-technical loss
-New business by using interactive
communication
-International connection based on
every country’s network
-Acceleration of renewable energy
-Improve non-technical loss
EU
-Fluctuation of Power (Frequency)
due to Wind power of large capacitor
in Denmark/Netherlands
-Construction of Infrastructure for
Electric Vehicle
High reliability of Power network due -Countermeasure when a lot of
to SCADA, DAS and redundant
network
renewable energy will connect to
Distribution network
-Energy management for consumer
side
Japan
Copyright © Tokyo Electric Power Services Co., LTD
12
1.2 Current Activities of oversea countries
Country
Power company
Plan for smart grid
-DAS has been operated in 6 areas in PEA
since 2004.
-DAS will be expanded to whole areas in
PEA by 2012. (In addition 7 areas)
-AMR has been operated in 30,000
customers in PEA.
-AMR will be expanded to 50,000
customers by 2012.
Thailand
-200MW of renewable energy has been
operated in PEA. (Biofuels: 60-70%, Solar:
5-10%, Wind power etc)
-DAS is under trial stage.
-AMR is also under trial stage.
-DAS will be applied to Ho Chi Minh city
by using Fiber Optic.
-Smart Grid including AMR / DR / Solar
will be applied to large city.
-Renewable energy will be increased up
to 5% by 2020.
-Solar power is installed in Quang Binh
province from 2010.
-Renewable energy (Wind /Solar /Biofuels
etc) is 3% of commercial electricity capacity.
Vietnam
India
-Indian government started to improve
Distribution loss and the reliability by
APDRP (10,000MUS$).
-DAS / AMR / GIS will be expanded to
large cities by using APDRP.
-Smart community city plan will be started
-DAS is under construction in Bangalore city. to apply for 4 cities as model projects.
This plan will be promoted by the support
of Japanese finance under construction of
high speed railway project.
-AMR and Pre-paid system have been
applied as model project.
Copyright © Tokyo Electric Power Services Co., LTD
13
2.1 Distribution Automation system
(DAS)
including Auto Meter Reading
(AMR)
Copyright © Tokyo Electric Power Services Co., LTD
14
Contents
1. Introduction of DAS
2. Advantages of DAS / DSM
3. Network System of DAS
• Overhead Network System
• Underground Network System
• Communication System
4. Distribution Automation SCADA System
Copyright © Tokyo Electric Power Services Co., LTD
15
1. Introduction of DAS / DSM /
AMR
Copyright © Tokyo Electric Power Services Co., LTD
16
What is DAS ?
• DAS improve reliability of Distribution power
utilities by reduction of outage duration.
- Automatic isolation of faulty section
- Quick Recovery for healthy sections
- Monitoring for distribution network in
real time
• DAS contribute to improve technical / non-
technical losses.
• DAS can connect to GIS (Giographic
Information System), AMR (Auto Meter
Reading) and DSM (Demand Side
Management).
Copyright © Tokyo Electric Power Services Co., LTD
17
Contribution to Society
Reduction of outage by DAS will…
• Attract Manufacturing Companies by improving and
ensuring the quality and their productivity
• Avoid Social Panic, such as hospital outage and
traffic stoppage
• Decrease of CO2 by diesel
engine which is used during
outage
Copyright © Tokyo Electric Power Services Co., LTD
18
Outage Time Around the World
(minute/year)
Figure. Average Outage Time per Customer
500
450
400
350
300
250
200
150
100
50
462
Key Point
- Japanese DAS provides the shortest
outage time in the world
- Japan has over 35 years experience on
Distribution Automation
90
77
58
4
0
Example (without
DAS)
USA
UK
FRANCE
JAPAN
(TEPCO)
India: 5,000 minutes in Bangalore (2005), Indonesia: 1,055 minutes in 2009
Reference: USA - IEEE Transactions on Power Delivery Jan.1999, UK - Ofgerm report 1999/2000 Jan. 2000
FRANCE - EDF Annual Report 2000, JAPAN - the Federation of Electric Power Companies (FEPC) report 2001
Copyright © Tokyo Electric Power Services Co., LTD
19
Japan’s Experience on DAS
Present Condition
1970
1980
1990
2000
Recloser System
Manual Switch
1972
O
V
E
R
H
E
A
D
Aim of Project
Oil Switch Vacuum Switch(VS) / Air Switch(AS)
⇒
Simplify DAS
Automatic Switch (VS/AS/GS)
VS/AS
⇒
DAS
SCADA System using Communication line
U
N
D
E
R
G
R
O
U
N
D
Manual Underground Switch (5ways)
Oil switch VS / AS
⇒
Automatic Underground Switch based on DAS
Copyright © Tokyo Electric Power Services Co., LTD
20
Tải về để xem bản đầy đủ
Bạn đang xem 20 trang mẫu của tài liệu "Bài giảng Green energy course syllabus - Chapter 7: Smart grid project - Nguyễn Hữu Phúc", để tải tài liệu gốc về máy hãy click vào nút Download ở trên
File đính kèm:
bai_giang_green_energy_course_syllabus_chapter_7_smart_grid.pdf